NC 55 Turn Lane (Avent Ferry to Main Street)

N.C. 55 near Avent Ferry RoadTransportation Bond-Funded Project

Adding new right turn lane southbound from Avent Ferry Road to South Main Street, improving traffic flow onto South Main Street.

Location:

N.C. 55 southbound from Avent Ferry Road to Main Street

Status: 

Completed

  • Signed contract with design consultant Summit Design & Engineering Services
  • Geo technical investigation
  • 25% completion stage of plan
  • Public meeting held in December 2019 (25% plan completion)

Underway

  • Utility coordination
  • Traffic study

Design

Estimated construction start:

2021

Public engagement:

A public engagement meetings were held in July and December, 2019.

Next steps: 

  • 2021: Construction begins

Key partners:

Holly Springs staff has engaged with key partners for this project, including:

  • North Carolina Department of Transportation
  • Capital Area Metropolitan Planning Organization
  • Duke Energy
  • United States Army Corps of Engineers/North Carolina Division of Environmental Quality

Contact:

Holly Springs Engineering: (919) 557-3938